Owner-side project controls on a brownfield EPC project
How an asset owner gets an independent, reliable view of schedule, cost and progress on an EPC brownfield project executed around live operations.
- Typical client
- Asset owner with an EPC contractor
- Services
- Project Controls, Advisory
- Timing
- Detailed engineering to mechanical completion
Where the project stands
An owner has awarded an EPC contract for a brownfield project on an operating site. Monthly reports from the contractor show the project on track, but site progress and tie-in dates suggest otherwise.
What makes it hard
- Contractor reports that the owner cannot verify
- Progress measured with rules the owner never agreed
- Tie-ins that depend on plant shutdown windows
- Forecasts that only change once the overrun is certain
How Surus works on it
- 01
Review
Assess the contractor baseline, schedule quality, rules of credit and cost reporting against the contract.
- 02
Define the rules
Agree progress measurement, schedule update and reporting requirements with the contractor.
- 03
Verify
Check progress claims and schedule updates every period, and run an independent forecast of cost and completion.
- 04
Report
Give owner management a short report with the real status, the main risks and the decisions needed.
What the client receives
- Baseline and schedule health review
- Agreed progress measurement rules
- Periodic verification of contractor progress and forecasts
- Independent cost and schedule forecast
- Owner management report
What changes on the project
- An owner view of the project that does not depend on contractor reporting alone
- Earlier warning of schedule and cost drift
- Tie-in dates aligned with plant shutdown windows
- Better-informed decisions on change and claims