Reports during a shutdown are often full of numbers but light on insight. The right KPIs are the ones that tell management, early enough, whether the event will finish on time and on budget — and what to do if it won’t. Here is a practical set, split between preparation and execution.
Preparation KPIs
Most turnaround problems can be predicted during preparation. These indicators show whether you are ready:
- Milestone adherence — percentage of preparation milestones met on time (scope freeze, work packs complete, contracts awarded).
- Work pack completion — share of work packs fully planned, reviewed and approved versus the plan.
- Late scope — number and estimated hours of work items added after scope freeze. A rising curve is an early warning of schedule growth.
- Materials readiness — percentage of required materials on site, especially for critical-path and long-lead items.
- Readiness score — a consolidated score from formal readiness reviews.
Execution KPIs
Progress versus plan
Physical progress should be measured with agreed rules of credit — for example, steps within a job weighted by their share of hours — rather than subjective percentages. Compare actual progress with the planned curve at every update.
Earned value indicators
- SPI (Schedule Performance Index) = earned value ÷ planned value. Below 1.0 means less work was completed than planned.
- CPI (Cost Performance Index) = earned value ÷ actual cost. Below 1.0 means the work is costing more than budgeted.
On shutdowns, SPI should be read together with the critical path: an overall SPI near 1.0 can hide a critical path that is slipping.
Critical path float
Track the remaining float on the critical and near-critical paths at every update. Shrinking float is often the clearest single signal that the end date is at risk.
Emergent work
Discovery work found after opening equipment is inevitable. Measure emergent work hours as a percentage of the original scope, and how much of it lands on the critical path. Comparing it with the contingency included in the plan tells you whether the schedule can absorb it.
Productivity and manpower
Compare actual manpower on site with the plan, and earned hours with spent hours. Low productivity usually has a cause that can be fixed: waiting for permits, materials, cranes or scaffolding.
Cost forecast
Update the estimate at completion (EAC) regularly, based on actual performance and remaining work — not just on the original budget. A forecast that only changes at the end is not a forecast.
Making KPIs useful
| Principle | In practice |
|---|---|
| Few and relevant | A one-page dashboard that management actually reads |
| Consistent | Same definitions and cut-off times at every update |
| Forward-looking | Forecasts and trends, not just status |
| Actionable | Every red indicator has an owner and an action |
Key takeaways
- Most shutdown overruns are visible in preparation KPIs — measure readiness, not just execution.
- Combine earned value with critical path float; neither is enough alone.
- Track emergent work explicitly against the contingency in the plan.
- Keep the dashboard short, consistent and tied to actions.