A turnaround is won or lost in preparation. By the time the unit is shut down, most of the decisions that determine duration, cost and safety have already been taken — or missed. A clear milestone timeline, counted backwards from the shutdown date (“T-0”), is the simplest way to keep preparation on track.
The timeline below is a typical structure for a major refinery or petrochemical turnaround. Smaller shutdowns and outages can compress it, but the logic stays the same.
T-24 to T-18 months: set the premises
- Turnaround premises and objectives — why are we shutting down, what must be achieved, and what are the targets for safety, duration and cost?
- Organisation — appoint the turnaround manager and core team, and define governance and decision rights.
- Milestone plan — publish the preparation schedule with all the milestones below, so every department knows what is expected and when.
- Long-lead items — identify equipment and materials with long delivery times early; this is where many turnarounds lose control of their critical path before they start.
T-18 to T-12 months: gather and challenge scope
Scope requests come from inspection, maintenance, operations, projects and process engineering. Every item should be justified by a clear driver: a statutory inspection, a reliability risk, a known defect or an approved project.
A scope challenge process — reviewing each item against its driver, its risk and whether it really requires a shutdown — is one of the most effective ways to control turnaround duration and cost. Work that can be done online, or deferred safely, should come out.
T-12 to T-6 months: freeze scope and plan the work
- Scope freeze — after this milestone, new work only enters through a formal late-scope approval process, with its cost and schedule impact visible to management.
- Work packs — detailed job plans with steps, resources, materials, drawings, isolations and permits.
- Contracting strategy — contractor packages, scopes and mobilisation plans.
- Integrated schedule — shutdown, mechanical and start-up activities in one network, with a realistic critical path.
T-6 to T-1 months: readiness
Readiness reviews at defined milestones check whether preparation is on track. A useful review looks at:
| Area | Key question |
|---|---|
| Scope | Is the scope frozen, and are late additions controlled? |
| Planning | Are work packs complete and reviewed? |
| Schedule | Is the critical path credible and resource-levelled? |
| Materials | Are long-lead and critical materials on site or on track? |
| Contractors | Are contracts awarded and mobilisation planned? |
| Safety & permits | Are isolation plans and permit processes ready? |
| Logistics | Are laydown, cranes, accommodation and access organised? |
Gaps identified here still have time to be fixed. Gaps discovered during execution usually become delays.
Execution: control around the clock
During execution, progress is updated typically every 12 or 24 hours. The focus is on protecting the critical path, controlling emergent work found after opening equipment, and reporting performance clearly to management every day.
Close-out: make lessons learned count
Close-out covers final cost, scope completion and a structured lessons-learned review. The most valuable part is also the most often neglected: turning the lessons into concrete changes for the next turnaround’s premises, scope process and planning standards.
Key takeaways
- Plan backwards from T-0 with published milestones.
- Challenge scope hard, then freeze it — and control what comes in late.
- Use readiness reviews to find gaps while there is still time to fix them.
- Close the loop: lessons learned should change how the next turnaround is prepared.